Schedule
(future days are planned, past dates are records)
January
- Fri, 08th: project description
- Tue, 12th: begin design phase; website created; confer with GNU
- Wed, 20th: infrastructure coding mostly there
February
- Mon, 01st: rough draft of proposal due
- Wed, 03rd: proposal presentations begin
- Wed, 10th: proposal presentations end
- Fri, 12th: final draft of proposal due
March
- Mon, 01st: reasonable testing possible; approx. version 0.1.0a
- Fri, 05th: rough draft of design due
- Mon, 15th: design presentations begin
- Mon, 22nd: design presentations end
- Fri, 26th: final draft of design due
- Wed, 30th: coding completed; approx. version 0.1.0b
April
- Mon, 19th: end testing phase
- Fri, 23rd: projected completion date; version 0.1.0
- Fri, 23rd: project documentation due
- Mon, 26th: final presentations begin
- Fri, 30th: final presentations end
|